Building a house,
stage by stage.

What happens in what order, roughly how long each part takes, and what to check before you let the next stage begin.

Building a house is a long sequence of decisions, and the expensive mistakes are almost always made by starting a stage before the previous one was finished. This is the order we work in and what each stage is for.

The stages

1 · Site and brief

The plot is surveyed and the rules that apply to it established. The brief — rooms, uses, budget, timeline — is written down rather than assumed. Ends when both sides agree on what is being designed.

2 · Concept design

Plans, massing and the central idea. Expect to revise. Ends with a layout you can picture living in.

3 · Design development

Structure, services and openings resolved; materials chosen; views produced for key spaces. Ends with a design that will not change without cost.

4 · Statutory approval

The drawing set is prepared in the authority's format and filed. Timelines here belong to the authority, not the architect.

5 · Construction drawings

Working drawings, details, schedules and specifications — the set the contractor prices and builds from.

6 · Tendering and appointment

Quotes taken on a common scope so they are comparable, then a contractor appointed. A cheap quote against a vague scope is not a saving.

7 · Foundation and structure

Excavation, foundation, columns, slabs. The least visible money you will ever spend and the most important.

8 · Masonry and services

Walls, then electrical and plumbing routed before plastering. Once it is plastered, changes get expensive.

9 · Finishes

Flooring, joinery, painting, fixtures. The stage clients enjoy and the one where programme slips quietly.

10 · Snagging and handover

A written list, chased to closure, before final payment. Warranties and as-built drawings collected.

How long it takes

For an independent house, design and approvals commonly take a few months and construction commonly takes a year or more, depending on size, site, weather and how promptly decisions are made. Anybody quoting a confident total before seeing the site and the brief is guessing. What can be committed to honestly is a stage plan with review points.

Where money is actually lost

Three places, in our experience. Changing the design after construction has started. Appointing a contractor on a scope too vague to hold anyone to. And leaving selections — tiles, sanitaryware, joinery finishes — until the site is waiting, which converts a design decision into a panic purchase.

What to check before each stage begins

That the previous stage is genuinely closed, in writing. A signed-off plan before structure is detailed. A frozen selection list before joinery is ordered. A measured verification before the slab goes up. These checks are unglamorous and they are what separates a project that lands on budget from one that does not.

Questions

Frequently asked

Do I need approval before starting construction?
Yes. Building without sanction risks penalties, demolition orders and problems at resale or when raising a loan. The drawing set is prepared for the authority's format and filed before work starts.
Can I start construction while the interiors are still being designed?
Yes, and that is normal — but electrical, plumbing and ceiling decisions must be settled before those trades reach them on site.
Should I buy materials myself?
Some clients do, for major items. It can save money and it always costs time and coordination. Decide deliberately rather than halfway.
What is snagging?
The final defect list before handover — every incomplete or badly finished item, written down, with responsibility and a date. Do not release final payment before it is closed.